How many concrete mixer trucks are needed for continuous pouring?
There are two things I’m most afraid of for continuous pouring: the concrete supply is cut off, and cold joints appear on the working surface; the cars arrive at the scene, and they are all blocked at the door and cannot be unloaded. The number of cars can’t be estimated by feeling, and it can’t be estimated only by distance.
Step 1: First, determine the actual pouring rate on site, and check the production capacity of the mixing station.
Only when all the prerequisites are met can the following calculation be meaningful: the concrete that can be produced by the mixing station per hour cannot be lower than the actual pouring rate on site m³/h. If this one doesn’t match, the number of cars calculated later will not be accurate.
The pouring rate cannot be directly copied from the output on the nameplate of the pump truck. The nameplate only marks the output under ideal working conditions. The repositioning of the placing boom, the vibration of concrete in layers, and the pipeline losses will reduce the actual speed. A pump rated at 60 m³/h may deliver only 35–45 m³/h when site operations stabilize. The actual value of the scene should be used, not the value on the nameplate.
Step 2: Calculate the actual load per truck using weighbridge data, without looking at the volume of the tank.
The geometric volume of the tank is not equal to the volume of finished concrete that can be transported to the construction site. The road weight limit and the allowable load of the whole vehicle will suppress the actual loading capacity, and a 12 m³ tank may only be loaded with 8 to 10 m³. Before signing the dispatching plan, the mixing station should be asked to report the actual load per truck using weighbridge data. The net weight of the concrete should be divided by the corresponding fresh concrete density, and the weight of the whole vehicle should not be used directly.
When the specifications of the fleet are not uniform, the feeding capacity of various vehicles should be calculated separately and then summed up. The hourly feeding capacity of each vehicle type = the number of vehicles of this type × the actual load per truck ÷ the complete cycle time in hours. The total should meet the actual pouring rate on the site.
Step 3: Calculate the complete cycle time one by one
The complete cycle of a car starts when it joins the loading queue at the station and ends when it returns to join the queue for its next load, and road transportation only accounts for one part of it.
| Stage | Content |
| Loading and departure from the mixing station | Entering the station and queuing, loading, and checking |
| Round-trip transportation | The outbound and return journeys are calculated according to the real traffic during the construction period, rather than the shortest time shown by navigation software. |
| On-site work | Check-in, waiting in line, reversing into position, unloading, and chute cleaning |
The three sections add up to the complete cycle time per truck. This value directly determines the number of cars. The finer the breakdown, the closer the result is to the scene.
Step 4: Use the basic formula to calculate the number of basic cars
The number of vehicles required = the actual pouring rate of the site × the complete cycle time per truck ÷ the actual load per truck based on weighbridge data
If the cycle time is recorded in minutes, it is divided by 60 to be exchanged for hours first, and the time unit must be unified. The calculated decimals should be rounded upwards and cannot be rounded to the nearest whole number.
The actual pouring rate of the site is 40 m³/h, the actual load per truck is 8 m³, and the complete cycle time is 90 minutes, which is 1.5 hours. 40 × 1.5 ÷ 8 = 7.5, and the basic configuration after rounding up is 8 units.
These 8 cars are the basic number of cars calculated according to the 90-minute complete cycle time, including the normal queue and waiting included in the measurement, and unexpected delays or vehicle failures have not been taken into account.
Step 5: Calculate the interval and hand it over to the mixing station for execution.
The planned truck arrival interval (minutes) = the actual load per truck based on weighbridge data ÷ the actual pouring rate on site × 60
Follow the above set of data: 8 ÷ 40 × 60 = 12 minutes. When giving instructions to the mixing station, it is more useful to report this interval than just report the total number of cars. If only “8 units” are specified, three units may be sent out from the station at once, leaving them all blocked at the door.
Step 6: Keep an eye on the upper limit of time, and add standby vehicles as needed.
The allowable unloading time limit and timing starting point of concrete should be determined according to the standards, technical requirements and supply agreement adopted by the project, and checked in combination with the mix design, temperature and workability retention. 90 to 120 minutes cannot be uniformly used, and the timing cannot be started from plant departure by default.
Do not use a fixed percentage for backup vehicles. In the urban peak congestion section, 1 to 2 units can be added as standby vehicles; if the route is smooth and loading capacity at the station is sufficient, there is no need to increase it.
Although the production capacity of the mixing station has been checked before the pouring starts, the raw material reserve and equipment status need to be confirmed again on the day of pouring. If the mixing station can’t produce concrete, no matter how many cars are sent, the supply will be cut off.
Step 7: After pouring starts, adjust according to the actual measurement
After the first few cars complete a cycle, you should write down the actual loading time, the time spent on the road, and the waiting time on site, and check it with the calculated value. If the cycle time is long, the reason should be judged first: when the transportation delay causes insufficient supply, vehicles can be added; when the on-site unloading slows down and vehicles queue, the dispatch frequency should be reduced. If the cycle time is shortened, the vehicles involved in the turnover can be reduced, but when the on-site pouring rate remains unchanged, the required arrival interval should still be maintained.
The number of cars is calculated according to the formula, the departure is controlled according to the interval, the production capacity is checked in advance, and the plan is adjusted in time according to the actual on-site measurement, so as to reduce the risk of supply interruption and vehicle backlog